1.1. Removal Procedure
2.1. Installation Procedure

Removal Procedure

Start By:

  1. Connect the steering frame lock. Refer to Disassembly and Assembly, "Steering Frame Lock - Separate and Connect".

  1. Park the machine on a flat, level surface. Lower the bucket to the ground. Chock the wheels in order to prevent the machine from rolling when the drive shaft is removed.



    Illustration 1g00979814

  1. Remove bolts (1) and remove straps (2) .



    Illustration 2g00979816

  1. Remove bolts (3) and remove straps (4). Remove center drive shaft (5) .

Installation Procedure


NOTICE

When the center drive shaft is installed, it must be installed in phase with the front and rear drive shafts. Serious component damage could occur. Be certain that all the joint group, all the yokes, and all the lubricating fittings are aligned.





    Illustration 3g00979816

  1. Carefully install center drive shaft (5) .

  1. Support center drive shaft (5). Install two straps (4) and bolts (3). The torque for bolts (3) is 71 ± 10 N·m (52 ± 7 lb ft).



    Illustration 4g00979814

  1. Install straps (2) and bolts (1). The torque for bolts (3) is 71 ± 10 N·m (52 ± 7 lb ft).

  1. Lubricate the rear drive shaft.

End By: Separate the steering frame lock. Refer to Disassembly and Assembly, "Steering Frame Lock - Separate and Connect".

Information System:

980G Series II Wheel Loader Braking System Hydraulic Oil Contamination - Test
2003/03/10 Explanation of Transmission Oil Temperature Sensors {5574}
2003/03/10 The Suction Line Filter Group for the Transmission is Relocated {3016, 3067, 3154}
TH220B, TH330B and TH340B Telehandlers Caterpillar Approved Work Tools
D6R Series II Track-Type Tractor Heating and Air Conditioning Control
TH350B, TH355B, TH360B and TH460B Telehandlers Lifting Capacities
938G Series II Wheel Loader and IT38G Series II Integrated Toolcarrier Power Train Modulating Valve (Transmission Clutch) - Install
2003/06/02 New Printer Is Used for Caterpillar Payload Control System (PCS) {749P}
938G Series II Wheel Loader and IT38G Series II Integrated Toolcarrier Power Train Modulating Valve (Transmission Clutch) - Remove
TH350B, TH355B, TH360B and TH460B Telehandlers Longitudinal Stability Indicator - Test
938G Series II Wheel Loader and IT38G Series II Integrated Toolcarrier Power Train Relief Valve (Transmission Hydraulic Control) - Assemble
D6R Series II Track-Type Tractor Reference Material
D6N Track-Type Tractor Machine Systems Bulldozer Control Valve - Remove
D6N Track-Type Tractor Machine Systems Bulldozer Control Valve - Install
D5N Track-Type Tractor Power Train Final Drive - Disassemble
D5N Track-Type Tractor Power Train Final Drive - Assemble
938G Series II Wheel Loader and IT38G Series II Integrated Toolcarrier Machine Systems Hydraulic Tank - Remove
938G Series II Wheel Loader and IT38G Series II Integrated Toolcarrier Power Train Differential and Bevel Gear - Install
D6R Series II Track-Type Tractor Reference Material
TH210 and TH215 Telehandlers Daily Inspection
938G Series II Wheel Loader and IT38G Series II Integrated Toolcarrier Power Train Drive Shaft (Rear) - Remove and Install
D11R Track-Type Tractor Safety Messages
938G Series II Wheel Loader and IT38G Series II Integrated Toolcarrier Power Train Transmission and Torque Converter - Separate
938G Series II Wheel Loader and IT38G Series II Integrated Toolcarrier Power Train Transmission and Torque Converter - Connect