938G Series II Wheel Loader and IT38G Series II Integrated Toolcarrier Power Train Relief Valve (Transmission Hydraulic Control) - Assemble Caterpillar


Relief Valve (Transmission Hydraulic Control) - Assemble
`

Assembly Procedure

Table 1
Required Tools 
Tool  Part Number  Part Description  Qty 
1P-1853  Retaining Ring Pliers 

Note: Cleanliness is an important factor. Before assembly, all parts should be thoroughly cleaned in cleaning fluid. Allow the parts to air dry. Wiping cloths or rags should not be used to dry parts. Lint may be deposited on the parts which may cause later trouble. Inspect all parts. If any parts are worn or damaged, use new parts for replacement.



    Illustration 1g00979416

  1. Install plug (16), fitting (15), and fitting (14) in body (12).


    Illustration 2g00979409

  2. Install ball (7), spring (6), and retainer (5) in spool (8). Use Tooling (A) to install retaining ring (13).

  3. Install slug (11), spool assembly (8), spring (9), and load piston (10) in body (12).


    Illustration 3g00979407

    ------ WARNING! ------

    Personal injury can result from being struck by parts propelled by a released spring force.

    Make sure to wear all necessary protective equipment.

    Follow the recommended procedure and use all recommended tooling to release the spring force.


  4. Install cover (4) and install bolts (3). Tighten bolts (3) to a torque of 28 ± 7 N·m (21 ± 5 lb ft).


    Illustration 4g00979403

  5. Install cover (2) and install bolts (1). Tighten bolts (1) to a torque of 28 ± 7 N·m (21 ± 5 lb ft).

End By:

  1. Install the relief valve. Refer to Disassembly and Assembly, "Relief Valve (Transmission Hydraulic Control) - Install".

Information System:

D6R Series II Track-Type Tractor Reference Material
D6R Series II Track-Type Tractor Operation
D5N Track-Type Tractor Power Train Track Roller Frame - Install
D5N Track-Type Tractor Power Train Track Roller Frame - Remove
TH220B, TH330B and TH340B Telehandlers Tire Shipping Pressure
938G Series II Wheel Loader and IT38G Series II Integrated Toolcarrier Power Train Relief Valve (Transmission Hydraulic Control) - Disassemble
938G Series II Wheel Loader and IT38G Series II Integrated Toolcarrier Power Train Torque Converter - Assemble - Fixed
TH350B, TH355B, TH360B, TH460B and TH560B Telehandlers Power Train Transmission - Remove
TH210 and TH215 Telehandlers Power Train Transfer Gears - Assemble
TH220B, TH330B and TH340B Telehandlers Specifications
938G Series II Wheel Loader and IT38G Series II Integrated Toolcarrier Power Train Relief Valve (Transmission Hydraulic Control) - Remove
938G Series II Wheel Loader and IT38G Series II Integrated Toolcarrier Power Train Torque Converter - Disassemble - Fixed
TH350B, TH355B, TH360B and TH460B Telehandlers Longitudinal Stability Indicator - Test
938G Series II Wheel Loader and IT38G Series II Integrated Toolcarrier Power Train Modulating Valve (Transmission Clutch) - Remove
2003/06/02 New Printer Is Used for Caterpillar Payload Control System (PCS) {749P}
938G Series II Wheel Loader and IT38G Series II Integrated Toolcarrier Power Train Modulating Valve (Transmission Clutch) - Install
TH350B, TH355B, TH360B and TH460B Telehandlers Lifting Capacities
D6R Series II Track-Type Tractor Heating and Air Conditioning Control
TH220B, TH330B and TH340B Telehandlers Caterpillar Approved Work Tools
2003/03/10 The Suction Line Filter Group for the Transmission is Relocated {3016, 3067, 3154}
2003/03/10 Explanation of Transmission Oil Temperature Sensors {5574}
980G Series II Wheel Loader Braking System Hydraulic Oil Contamination - Test
938G Series II Wheel Loader and IT38G Series II Integrated Toolcarrier Power Train Drive Shaft (Center) - Remove and Install
D6N Track-Type Tractor Machine Systems Bulldozer Control Valve - Remove