For implement coupler tools not requiring third valve hydraulics
![]() |
If operator or any person is in the cab and at the controls, clear all personnel from the machine and the area while performing all steps listed in operating techniques. |
![]() |
Attaching Front Implements
- 1. Disengage the coupler locking pins by moving and holding the coupler control switch to the unlock position. (see fig. 1)
Fig. 1
- 2. Engage top coupler tube into implement top hooks by tilting the coupler forward. Tilt the coupler forward by pushing tilt lever forward. (See fig 2)
Fig. 2
NOTE: Make sure that the top coupler tube is below the level of the hooks on the implement to be attached by adjusting the loader arm height
- 3. Drive machine forward slowly, aligning the implement hooks with the coupler tube.
- 4. Pull the lift lever back to slightly raise coupler. Raise loader arms until coupler tube contacts the implement hooks and implement is lifted slightly.
NOTE: Make sure the implement is level from side to side.
- 5. Align implement retaining holes with coupler pins by pulling the tilt lever back until the implement squarely rests against the coupler face.
- 6. Engage coupler locking pins into implement retaining holes by moving the coupler switch to the lock position. (see fig. 1)
NOTE: Visually check that the coupler locking pins are engaged into implement retaining holes (see fig. 2). Insure implement is engaged by following steps 7 through 9
- 7. Push the tilt lever forward to tilt the implement down.
- 8. Push the tilt lever forward to put down pressure on the implement.
- 9. Back the machine and make sure there is no movement between the implement and the coupler.
NOTE: This is the only positive indication that the coupler locking pins have fully engaged the implement retainer holes.
![]() |
Improper attachment of implements could result in injury or death. Do not operate this machine until you have positive indication that the coupler pins are fully engaged. |
![]() |